Checklist for Avaya Aura System Manager switchover

Last Updated : Dec 14, 2022 |
Note:

For partial switchover of Avaya Oceana® and Avaya Analytics™ applications, do not perform System Manager switchover. System Manager switchover is required only for a full DR switchover or a failure of the actual primary System Manager.

Note:

The procedure to bring the DR System Manager into production involves disabling operational geographic redundancy replication and shutting down the primary System Manager. There is no switchover from the primary System Manager application to the DR System Manager application.

No.

Task

Description

1

Disable the Geographic Redundancy replication.

Disable Avaya Aura® System Manager Geographic Replication at Data Center 1.

Disabling the Geographic Redundancy replication

2

Shut down System Manager at Data Center 1.

You must shut down Avaya Aura® System Manager to trigger the Avaya Breeze® platform snap-ins to switch to the System Manager instance at Data Center 2.

Shutting down System Manager from the web console

3

Activate System Manager at Data Center 2.

Activate Avaya Aura® System Manager at Data Center 2.

Activating the secondary System Manager server

4

Verify the Avaya Breeze® platform node controller.

Confirm that the Avaya Breeze® platform nodes are switched from System Manager in Data Center 1 to System Manager in Data Center 2.

Verifying Breeze node controller