The following is a checklist of the preparation and validation steps before you perform a partial controlled switchover.
No. |
Task |
Description |
![]() |
|---|---|---|---|
1 |
Prepare for switchover - Before starting any switchover operations on a production Avaya Oceana® and Avaya Analytics™ DR system, you must refer to several key documents. |
||
2 |
Validate identical software levels on the following applications across DC1 and DC2:
|
||
3 |
Validate Avaya Oceana® solution replication before switchover. |
||
4 |
Validate Avaya Aura® System Manager primary to DR replication status and health status from DC1 to DC2 is fully operational. |
Validate the System Manager primary to DR replication status. |
|
5 |
Validate Avaya Aura® System Manager and Avaya Breeze® platform replication status to all Avaya Breeze® platform nodes in DC1 and DC2. |
See Validate the System Manager and Avaya Breeze platform replication status. |
|
6 |
Validate the Avaya Control Manager database HA replication status. |
See Validating the Avaya Control Manager database HA deployment. |
|
7 |
Verify the Context Store replication status from DC1 to DC2. |
||
8 |
Verify the Omnichannel database mirroring status from DC1 to DC2. |
||
9 |
Verify Avaya Aura® Communication Manager to ESS data replications. |
See Verifying Avaya Aura Communication Manager to ESS data replications. |
|
10 |
Verify the Avaya Analytics™ DB Replication from DC1 to DC2. |
See Verifying the Avaya Analytics DB replication from DC1 to DC2. |
|
11 |
Validate snap-in shutdown or deployment status in the DR site. |
See Validate Avaya Oceana snap-in shutdown or deployment status in DC1 and DC2. |
|
12 |
Verify UCA replication status from DC1 to DC2. |
||
13 |
Verify the deployment status of EmailService in DC2. |
||
14 |
Verify the shutdown status of CustomerControllerService in DC2. |
See Verifying the shutdown status of CustomerControllerService in DC2. |
|
15 |
Verify the shutdown status of MessagingService in DC2. |
See Verifying the shutdown status of MessagingService in DC2. |
|
16 |
Verify the shutdown status of GenericChannelAPI in DC2. |
See Verifying the shutdown status of GenericChannelAPI in DC2. |
|
17 |
Verify the deployment status of the AMC snap-in for Avaya WebRTC Connect. |
See Verifying the deployment status of the AMC snap-in for Avaya WebRTC Connect. |
|
18 |
Verify the CSC deployment status in DC1 and DC2. |
See the following:
.
|
|
19 |
Launch Oceana Monitor for DC1 and DC2 locations and verify there are no un-deployed PUs across all Oceana clusters. |
See the following: |
The following is a checklist of the list of steps to perform a Partial Controlled Switchover.
No. |
Task |
Description |
![]() |
|---|---|---|---|
1 |
Configure the primary site voice channel shutdown. |
||
2 |
Configure the primary site email shutdown. |
||
3 |
Configure the primary site chat shutdown. |
||
4 |
Configure the primary site MessagingService shutdown. |
||
5 |
Take a backup of UCAStoreService and UCMService (on remote server). |
See Taking a backup of UCAStoreService in Data Center 1 and Taking a backup of UCMService. |
|
6 |
Configure the primary site GenericChannelAPI service shutdown. |
See Configure the primary site GenericChannelAPI service shutdown. |
|
7 |
Set the maintenance mode for front end web voice and web video. |
See Setting the maintenance mode for front end web voice and web video. |
|
8 |
Switch to DR site Oceana and POM system. |
||
9 |
Validate contacts in DC1. |
See Validating contacts. |
|
10 |
Log out supervisors and agents from DC1. |
||
11 |
Change the cluster activity status for clusters in DC1. |
See Changing the Cluster Activity status for the clusters in Data Center 1. |
|
12 |
Switch over the Omnichannel database server in the primary site DC1 to the Omnichannel database server in the DR site DC2. |
See the following: |
|
13 |
Switch over Avaya Analytics™ from DC1 to DC2. |
The following checklist lists the configuration and validation steps after you perform a partial controlled switchover.
No. |
Task |
Description |
![]() |
|---|---|---|---|
1 |
Verify CSC deployment status in DC2. |
||
2 |
Restore the UCMService data for Avaya Oceana® cluster 1 in Data Center 2. |
See Preparing UCMService in DC2 for database restore See Restoring the UCMService data for Avaya Oceana Cluster 1 in Data Center 2. |
|
3 |
Configure the DR site EmailService startup. |
||
4 |
Configure the DR site Chat startup. |
||
5 |
Configure the DR site MessagingService for Social or SMS startup. |
See Configure the DR site MessagingService for Social, SMS or Async startup. |
|
6 |
Configure the DR site GenericChannelAPI Service startup. |
See Configure the DR site GenericChannelAPI Service startup. |
|
7 |
Verify DR Application Enablement Services server to enable switch connection. |
||
8 |
Change the cluster activity status for clusters in DC2. |
See Changing cluster activity status for clusters in Data Center 2. |
|
9 |
Avaya Workspaces Agent switchover: Login Agents using DC2 Workspaces and test deployed Channel Routing. |
||
10 |
Use the Toggle button to switch Avaya Control Manager in DC 1 to use Avaya Oceana® applications in DC2. |
||
11 |
Validate and test deployed channels: Launch Oceana Dashboard and verify all deployed channels are in the Green status. |