Use the following checklist for the tasks that you must complete before migrating to Avaya Context Store Snap-in 3.10.0.2:
No.
Task
Notes
1
Take a snapshot of Context Store, Engagement designer Avaya Breeze® platform servers, and Avaya Aura® System Manager before performing any activity.
Note:
Skip Engagement designer Avaya Breeze® platform servers if engagement cluster is not part of the deployment.
Perform this step if the customer decides to fallback to the previous release of Avaya Oceana®.
2
Set the cluster state of all clusters to Denying.
3
Record Avaya Breeze® platform identity certificate and third-party certificate information.
Note down the information about the following certificates:
  • Security Module HTTPS
  • Security Module SIP
For more information about accessing these certificates, see Chapter Configure certificates in the Deploying Avaya Oceana® documentation available on Avaya Support website at https://support.avaya.com.