Ensure that the customer completes the following before deploying the Communication Manager KVM Open Virtualization Application (OVA) on Avaya-supplied Avaya Solutions Platform 130.
#
Task
Description
1
Identify the hypervisor and verify that the capacity meets the OVA requirements.
2
Plan the staging and verification activities and assign the resources.
3
Download the required Avaya Aura® OVA.
4
Download the latest Communication Manager patch (Service Pack or Feature Pack).
Solution Deployment Manager Client does not support KVM on RHEL 8.10 or KVM on RHEL 9.6 images for a virtualized environment.
With the introduction of Avaya Solutions Platform R6.0.x there is no longer a specific license key needed as was present with Avaya Solutions Platform 5.1.x and earlier versions running on ESXi. However, it is imperative that customers have a record in PLDS for each and every instance of the server hypervisor as customers and Avaya will be subject to audits to ensure right to use royalties have been paid.