Planning checklist for VMware®

Last Updated : Dec 28, 2024 |
Prolog information
Ensure that the customer completes the following before deploying the Communication Manager Open Virtualization Application (OVA) on Customer-provided VMware or Avaya-supplied Avaya Solutions Platform 130.
#
Task
Description
1
Identify the hypervisor and verify that the capacity meets the OVA requirements.
2
Plan the staging and verification activities and assign the resources.
3
Purchase the required licenses.
Register for PLDS and perform the following:
  • Obtain the license file.
  • Activate license entitlements in PLDS.
Go to the Avaya Product Licensing and Delivery System at https://plds.avaya.com/.
4
Download the required Communication Manager OVA.
5
Download the latest Communication Manager patch. For example: 00.0.441.0-XXXXX.tar.
For information about VMware features supported by Avaya Aura®, see VMware features supported by Avaya Aura