Fulfill the following prerequisites for POM High Availability:

  • Ensure that the database is accessible from all operational POM servers.

    Note:

    Customers must administer the POM database if they install the schema on a local or an external database.

  • Deploy POM in a multi-server deployment model.

  • Deploy the application server on a standalone server.

  • Deploy Media Processing Platform as a standalone server.

  • Ensure that you synchronize the time on all POM servers with the time on the Network Time Protocol (NTP) server.