Enabling a survivable core server from the main server

Last Updated : Aug 19, 2013 |

About this task

You can expect the following events to occur:
  • Communication Manager resets on the survivable core server being tested.

  • Once the survivable core server resets it re-registers with the main server.

  • The survivable core server receives a translation download from the main server and resets again.

  • After the reset, the survivable core server re-registers with the main server.

Use this procedure to test the ability to enable a survivable core server from the main server. Perform the following step to execute this test.

Procedure

On the main server, execute the enable ess cluster <cluster ID> command.