1.
|
Understand and plan for the upgrade
|
Read this document in full and understand all the requirements before taking any other actions.
-
-
IP Office R11.1 does not use Windows servers to host its services. If using any such servers, for example for Avaya one-X® Portal for IP Office or Voicemail Pro, they must be replaced with Linux-based servers. See Windows Server migration
|
|
2.
|
Back up the server(s)
|
Before upgrading to R11.0.4.8, back up the IP Office servers and services.
|
|
3.
|
Upgrade to the latest R11.0.4 service pack
|
Upgrade the Linux-based IP Office server(s) to R11.0.4.8 using the standard ISO file transfer methods.
|
|
4.
|
Verify Correct Operation
|
After upgrading to R11.0.4.8, verify the operation of all services.
|
|
5.
|
Backup the server(s)
|
Before upgrading to R11.1.3, back up all the IP Office servers and services.
|
|
Upgrade to the latest R11.1 service or feature pack
|
Proceed with the upgrade from R11.0.4.8 to R11.1.3 using the special one-off upgrade processes in this document.
|
|
|
This process uses a USB memory key created using the R11.1.3 ISO file.
|
|
|
This process uses a USB memory key created using the R11.1.3 ISO file.
|
|
|
This process uses a virtual hard disk (vmdk) file downloaded from Avaya. You can use the file to reboot and upgrade the server.
|
|
|
This process uses a virtual hard disk (vhd) file downloaded from Avaya. You can use the file to reboot and upgrade the server.
|
|
|
This process uses a virtual hard disk (vmdk) file downloaded from Avaya. You can use the file to reboot and upgrade the server.
|
|
6.
|
Verify the upgrade
|
After upgrading to R11.1.3, verify the operation of all services except Media Manager.
|
|
7.
|
Restart Media Manager
|
If the server needs to supports Media Manager, restart the service. This starts the database encryption process.
|
|
8.
|
Update any other servers
|
|