Before upgrading, refresh elements on the Upgrade Management page.
Before you begin
On the User Settings page, configure the user settings.
  1. On the System Manager web console, click ServicesSolution Deployment Manager.
  2. In the navigation pane, click Upgrade Management.
  3. On the Upgrade Management page, do the following:
    1. Select one or more devices.
    2. Click Pre-upgrade ActionsRefresh Element(s).
  4. On the Job Schedule page, click one of the following:
    • Run Immediately: To perform the job.
    • Schedule later: To perform the job at a scheduled time.
  5. If you selected Schedule later, select the date, time, and timezone.
  6. Click Schedule.
    STEP RESULT:
    The Last Action Status column displays and the Current Version column displays the current version of the element.