Testing the recovery process

Last Updated : May 05, 2020 |
Prolog information
  1. Turn off power to the Usage Metering server in the primary data center.
  2. Delete the old Usage Metering server instance from the primary data center.
  3. Recover Usage Metering in the secondary data center.
    ADDITIONAL INFORMATION:
    For more information, see Secondary data center recovery process.
  4. Verify the following:
    ADDITIONAL INFORMATION:
    • Usage Metering starts collecting usage data.
    • Usage Metering sends alerts to SAL GW and SNMP Trap Host.
  5. Turn off power to the cold standby Usage Metering server.
  6. Delete the secondary cold standby.
  7. Recover the Usage Metering server on the primary data center.
  8. Prepare the cold standby.
    ADDITIONAL INFORMATION:
    For more information, see Preparing a cold standby server.