status periodic-scheduled

Last Updated : Nov 13, 2020 |

Use status periodic-scheduled to see summary information about currently active and recently completed background testing. Periodic tests run every hour, and scheduled tests run daily. Starting and stopping times, and other parameters for daily scheduled testing, are administered with change system-parameters maintenance.

Syntax

status periodic-scheduled 

status periodic-scheduled field descriptions

Field

Description

PERIODIC MAINTENANCE section

This data reflects the status of periodic maintenance which is performed hourly, according to the selections made on the change system-parameters maintenance screen. See Maintenance Alarms for Avaya Aura® Communication Manager, Branch Gateways Servers for more information.

Pre-SCHEDULED MAINTENANCE section

The data in this section reflects the status of pre-scheduled maintenance. Pre-scheduled maintenance can include interchanges of duplicated components and backup of translation data. It is performed according to selections made on the change system-parameters maintenance screen.

SCHEDULED MAINTENANCE section

The data in this section reflects the status of scheduled maintenance which is performed daily. Scheduled maintenance is performed according to the selections made on the change system-parameters maintenance screen.

System Critical

System-critical resources are those whose health affects the entire system such as the processor. These are always tested first.

Shared Resource

Shared resources are those that are used by many users, such as trunks. These are tested after system critical resources.

Single User

Single-user resources are those whose health affects only one user, such as voice stations.

Total

Total duration of previous periodic or scheduled maintenance cycle. Note: Scheduled maintenance total does not include pre-scheduled maintenance duration.

Current Cycle % Complete

The ratio of the number of maintenance objects tested to the total number of maintenance objects tested during a cycle. For periodic tests, the ratio is for the current cycle, if active; or for the last completed cycle if not. For scheduled tests, the ratio is for the last completed cycle.

Current Cycle Active

Reflects whether the current cycle of periodic, pre-scheduled or scheduled maintenance is currently running. Value is y if currently running or n if it is not.

Previous Cycle Duration

Reflects how long the system critical, shared resource, or single user maintenance activities took for the previous cycle of maintenance.

Rate of Completed Cycles

Reflects how often maintenance cycle is performed.

Start Time of Current or Previous Cycle

Time at which maintenance cycle began in month/day/hour:minute:second format. For scheduled maintenance, this time reflects when the pre-scheduled maintenance began.