display test-schedule

Last Updated : Apr 05, 2018 |

Use display test-schedule to see the test schedule for an S trunk.

Automatic Transmission Measurement System (S) provides advanced maintenance procedures for monitoring system trunk facilities. This system performs transmission tests on system trunks to determine whether trunks are performing satisfactorily.

Syntax

display test-schedule 

display test-schedule field descriptions

Field

Description

Schedule

The current schedule number.

Schedule Time

The hour and minute that the test begins (24-hour time, with 00:00 being midnight). This time must be greater than the current time.

Schedule Date

Month (1 to 12), day (1 to 31), and year on which testing begins (default is the system date). This date must be equal to or greater than the current date.

Schedule Test Days

y next to the days of the week indicates which days of the week this test runs.

Interval

The length of this schedule in weeks. If 0, the schedule runs on the specified days only once.

OTL Throttle

The number of trunk members (1–4) tested concurrently during a schedule. If this field is set to 1, the OTL (originating test line) tests each trunk sequentially. If set from 2–4, the specified number of trunks are tested in parallel.

Test Type

One of the following types of test to be performed on the trunk group/ members in this schedule:

  • full — runs the most comprehensive test and collects every associated measurement for each TTL type.

  • supv — performs a supervision test and only confirms the presence of the test set at the far end. No measurements are taken for this test.

  • no-st — runs the full test, but skips any self-test sequences. This saves about 20 seconds on the type 105 test and does not have any effect on type 100 or 102 tests.

  • no-rl — runs the full test, but skips any return-loss sequences. This saves about 20 seconds on the type 105 test and does not have any effect on type 100 or 102 tests.

  • no-st/rl — runs the full test, but skips every self-test and return-loss sequence. This saves about 40 seconds on the type 105 test and does not have any effect on type 100 or 102 tests.

Duration

The maximum number of hours (1 to 24) a schedule can remain active. Schedules continue to run until every trunk group/member for that particular schedule is tested or until the scheduled duration elapses. If the duration elapses before every trunk group/member can be tested, the schedule stops.

Trk Trp

The trunk-group numbers to be tested when this schedule runs. There is no limit to the number of times that a trunk group can be displayed on any particular schedule, or to the number of different schedules in which a trunk group can be displayed. Default is blank.

Bgn Mbr

The beginning member number of the trunk group to be tested; default is 1.

End Mbr

The ending member number of the trunk group to be tested. This value must be greater than or equal to the value of the beginning member field.