Resources assigned to a zone can be moved from one zone to another zone. However, there are certain restrictions for moving a resource from one zone to another.
|
Resource
|
Restrictions
|
|
Applications
|
No applications can be moved from one zone to another.
|
|
Organizations
|
No applications are configured in the zone from which the resource is being moved.
|
|
Auxiliary EPM servers
|
If a co-resident SMS processor uses an SMPP connection which is not shared, changing zones is not possible.
|
|
Media servers
|
The media server being moved must be stopped.
|
|
ASR servers
|
All media servers are stopped in the zone from which the resource is being moved.
|
|
TTS servers
|
|
H.323 connections
|
|
SIP connections
|
|
SMPP connections
|
All auxiliary EPM servers must be stopped in the zone from which the resource is being moved.
|
|
HTTP connections
|
|
Email connections
|