BRI Set Audits Test (#630)

Last Updated : Oct 27, 2014 |

This is a series of tests that are classified as audits. The switch sends messages to the BRI endpoint to perform the following tests:

  • Ringer Audit – This audit verifies that both the switch and the endpoint agree as to the current state of the endpoint’s ringer.

  • Lamps Audit – This audit verifies that both the switch and the endpoint agree as to the current state of the endpoint’s lamps.

  • Call Activity Audit – This audit verifies that the state of calls is consistent between the switch and the endpoint.

This test is not executed for ASAI or Avaya adjunct because adjuncts do not employ ringers or lamps and do not establish calls on the B-channels associated with the BRI interface.

This test is run on BRI-SET, Various Adjuncts.